Project Scope
The Maldives Project consists of 57 staff dormitory buildings with one to two-story, comprising a total of 531 modules. The total construction area of the project is 13,234 square meters.
Project Introduction
The internal systems, including plumbing, electrical wiring, sanitary fixtures, and furniture, are all completed at the manufacturing facility. Meanwhile, the fire protection system and external wall cladding will be installed on-site. The modules will be shipped to the Maldives project site by sea.
The entire project, from design to production completion, was accomplished in just 130 days.